How to Apply for a Building Permit for Residential In Mali

Apply for a Building Permit for Residential In Mali By Yourself

  1. The applicant must visit the general secretariat of town hall located in your area and register your desire by contacting the desk at front;
    • Complete the forms you require and complete them.
    • Attach all required documents (see the required documents below for the required document) Also, attach all the required documents (see required document below)
    • Submit the documents for verification and recorded.
  2. When the official is convinced it is all in good order, he or she will forward the file at the counter for cash. and you’ll be asked to pay the administrative costs, following which you will be presented with an acknowledgement receipt.
  3. The petitioner will receive an acknowledgement of the date on which you retracted the request for response and the receipt to pay all costs associated with the investigation.
  4. The application file will be sent by the permit issuance authority, which has the three (3) work days in which to forward the file into the Town Planning and Construction department to analyze and provide advice.
  5. When the file is received, the department of town planning and construction will look into the following area of construction materials, water, electrical, and telephone management organizations’ within three (3) working days following the date of receiving the file. The department will then forward it to interested companies and services that they convene in a meeting to decide in seven (7) working days after receiving the file.
  6. The department for town planning and construction is given the right to three (3) day working hours starting from on the day of the event to provide the authority for building permits its reasoned decision on the application.
  7. When the recommendation is received after which the building permit issuing authority will then review the application and take the decision to grant or deny the request . They will inform the applicant about the outcome within three days.
  8. If, within the specified timeframe, the applicant hasn’t received any action, the applicant may send a letter of protest to the authority that issue the permit for building with the details of the original request.
  9. The authority in charge must provide an answer in no more than 8 (8) day calendar from the date of the receipt of the complaint letter.
  10. After all notifications of the result are received after which the Regional Director sends the authorization’s wording in writing to the municipal mayor for approval. in the event that it is it is approved.
  11. The file is then forwarded on to Regional Planning Directorate for the technical visa affix, as well as to redraw the permit to applicants at the office for building permits after the payment of all necessary fees.

Required Documents For Apply for a Building Permit for Residential

  • The letter addressed to the mayor should in clude the following details:
  • Names First names, professions nationality, address and names for natural individuals.
  • The name and/or company name for the community, service, company or organization for legal private or public individuals.
  • The place of works of modification or construction as well as the areas that are traversed by the networks and tracks.
  • The purpose, nature as well as the description for building.
  • The estimated cost of the work
  • Application is stamped with 250 CFA dollars addressed to the Mayor.
  • A title deed or other legal evidence of the right to use the applicant.
  • A technical file that has at minimum seven (7) copies, including:
    • A plan of the site under construction, on a scale of 1 or 2000th.
    • A ground plan of minimum one-half of a scale.
    • Sections and plans at the ratio of 1/50th, for structures whose plan span or height is not more than 30 (30) meters, and at 1 / 100th for structures that have wingspans larger than this size.
    • A detailed descriptive quote.
    • Formwork and calculation plans for building projects where the distances between axes on the load-bearing elements in the vertical direction are greater that five (5) meters as determined by an authorized consultant engineer.
    • An explanation of the testing of soil and rationale that the foundation is necessary constructions with levels higher than three, and those with basement provision.
    • An inspection contract to monitor construction projects that requires the calculation of a note as well as soil tests.
    • Plan of the sanitation system.

Office Locations and Contacts

Mali Contacts for City/Town Halls’

  • Kolongo – tomo

Address: Macina, MaliTelephone: +223 07 25 82 05

  • Commune V Mayor

Address: Bamako, Mali

  • The Mayor of Niamakoro

Address: Bamako, Mali
Phone: +223 76850506

  • Central Hall of the common IV

Address: Bamako, Mali
Phone: +223 76141147

  • Mairie M’Pessoba

Address: RN10, Mpessoba, Mali
Phone: +223 21645010

Eligibility

The following people/construction industries are eligible for construction/Building Permit.

  • civil engineering;
  • structural engineering;
  • architecture;
  • Building services;
  • Building surveying;
  • Quantity surveying
  • Construction management

Fees

Legal Fees

  • 10,000 CFA francs for administration costs.

Please be aware that the cost of fees varies depending on the municipality.

Validity

The validity period that the construction permit has extends for the period of one (1) year from the date of signing. If the owner of the permit is unable to begin building work within the allowed time frame, he can apply for an extension for one (1) month prior to the expiration date of the permit. In the event that he is not able to start construction, he can apply for a new construction permit.

Processing Time

The processing period is between 19 working days.

Requirements Information

  • Names First names, professions addresses, nationality, and names for natural individuals.
  • The name and/or company name for the community, service, company or organization for private or public legal people.
  • The place of construction or alteration works and the areas that are crossed by the networks and tracks.
  • The location, the nature along with the details of the structure.
  • The address of the location where the construction is planned to be completed.
  • The applicant’s declaration
  • Contact information of the applicant’s contact information
  • The estimated cost of the work

The Document is required

The Residential Building Permit (BPL) is an official document that gives formal permission to the person applying to commence the construction, demolitionor addition , or renovation of the residential dwelling of the resident.