How to Apply for a Electricity Connection In Mali

Apply for a Electricity Connection In Mali By Yourself

  1. The applicant should go to The Energie du Mali branch agency close to you and register your desire at the desk of customer service.
    • Gather the necessary forms and correctly fill themin;
    • Attach all required documents (see the document required below for the required document) Also, attach all the required documents (see required document below)
    • Send the documents to be checked and then registered with an EDM agent.
  2. Then, you will be required for payment of the fee to the money desk at which point you will receive an acknowledgement slip as well as an appointment for a site inspection within 15 days.
  3. The application file is transferred to the technical service to be studied by technical sales agents as well as the quantity surveyors.
  4. It is the EDM will then send a surveyors to check the’residence’ to ensure the standards are in compliance. The authorized officer will calculate the amount you’ll have to pay for the connection , and issue an invoice.
  5. The document and receipt for payment are returned at the desk of reception to be given to the applicant who will then decide the time and date to pay payment for the connecting fee.
  6. If you are in agreement to pay the receptionist fills out and signs the contract form , and deliver it to the manager of customer service for their signature.
  7. The file is stored on the computer and transferred to the cash register , where you will be asked to pay against the receipt for connection.
  8. When you pay, you’ll receive an invoice for payment along with an original contract copy.
  9. The file is sent to accounting to assist with the journaling of receipts. A second copy is given to technical service , and another copy is filed with customer service.
  10. The technical service team will visit the home for exterior work, installation of meters and electric flow within 15 days.
  11. Once you have completed the installation, an installation form for the meter is issued from the tech support team to mark and then insert into the file. The file will be sent to the reception department to update and invoice.

Required Documents For Apply for a Electricity Connection

Supply to residential properties

  • National Identity Card of the applicant or Passport ID
  • An original copy of title deed for the applicant
    • A duplicate of the Lease arrangement, in the event that the applicant lives on State Land;
    • A copy of the transcription, if the land was transcribed to the applicant
    • A letter of authorisation from the landlord, in case you are a tenant, and an original copy of the landlord’s title deed
  • Building and Land Use Permits for the mentioned premises, if the permit is required.
  • A list of electrical appliances that can be connected to in Watts (W) (kW) or Kilowatts (kW)
  • Please note: If you’re renting the space as tenant, the authorization from the landlord is required along with a copy of his National Identity Card and Title Deed.

Supplies for Non-residents (Commercial or Industrial Purposes).

  • A signed letter from the company asking for the new supply, including the load to be connected;
  • A list of all approved electrical equipment that must be connected in Kilowatts or watts;
  • The firm’s Business Registration Card together with the Certificate of Incorporation.
  • A duplicate of the Title Deed in case of the ownership of the property
  • A letter of authorization from the landlord or replica of the Lease Agreement if the customer is a tenant, as as a copy of the relevant Title Deed;
  • An application for a Building or Land Use Permit where applicable.
  • If an officially registered business it is necessary to provide a list of shareholders( the ones who own more than 10 percent of shares) and
  • National Identity Card issued by the Director, or Passport ID.

Please be aware that the EDM reserve the right to request additional documents as needed.

Office Locations and Contacts

Siege Energie Du Mali Headquarter
Address: Square Patrice Lumumba, Bamako, Mali
Telephone: (+223) 20223060/ 20223020
Fax: (+223) 20228430

Eligibility

Service is open to all , but the applicant must meet the following conditions

  • Ground
  • Set up a fuse box or circuit breaker
  • Provide for connection after meter,
  • Complete the ceiling on the exterior and put up the exterior wall to the counter.
  • Create a power analysis in agencies (calculation on the amount of equipment we intend to employ).

Fees

You will receive a receipt that identifies your connection cost (quotation fee) as well as the security deposit fee that is required from the EDM.

Validity

The validity of the connection lasts indefinite, unless you fail to pay the electricity bill. This could can result in the termination from the power service.

Processing Time

The installation time is 15 days after the payment of the connection fee

Requirements Information

  • Information about the applicant
  • Details of the address at which the supply is needed
  • The type of the premise
  • The use of the premise
  • Name /address of employer/business/reference person (where applicable)
  • Identification number
  • The applicant’s declaration
  • Nearest power source close to your home

Documentation is needed

Person/business/company that wish to apply for electricity connection in Mali should visit the Energie du Mali agency and file the application

External Link

Link

How to Apply for a Electricity Connection In Mali
How to Apply for a Electricity Connection In Mali

Source

Link

Leave a Comment