  • Send your application to Municipal Electric Power Company and attend to the power supply plan as well as estimate.
  • Pay the estimated amount to Municipal Electric Power Company, and have the design plan for an external connection evaluated.
  • Buy the materials and then install them.
  • Submit the report in writing to Municipal Electric Power Company and attend the an internal and external final examination.
  • Receive installation of the meter and the connection with grid.

Documents that are required Getting Electricity

  • Completed application form with all the details
  • Sketches of your home as well as the number for your account of your neighbor, in the event that he/she is connected to electricity.
  • Service type (domestic or commercial)
  • A stamp of a company in the case of a business
  • Evidence of ownership of an owner
  • Tenancy agreement as well as passport size photograph from the tenant (for tenants)
  • Identity proof that is valid

Office Locations and Contacts

Department of International CooperationAddress No.1 Lane 2, BaiguangRoad, Xicheng Directrict, Beijing, China
Tel: 8610-63415533, 8610-63415230
Fax: 010-63545305
E-mail: cecintl@cec.org.cn
Website: www.cec.org.cn
Map
Governing units

What Are All The Eligibility

  • Individuals who are applying for use in the home

Manufacturing or construction companies are eligible to get generate power.

Instructions

An electrician who is skilled enough to be able to visit your home to check for proper wiring insulation, wiring and earthing processes. The person who is licensed by distributors to examine the electrical wiring system in the premises.

The Information You Need

  • Full name
  • Zone
  • Service type (domestic or commercial)
  • Telephone number
  • Birth date
  • Identity proof that is valid
  • Citizenship
  • Address
  • Occupation
  • Passport size photo with white background
  • A company stamp on the case of a business
  • Evidence of ownership in the case of the original landowner.
  • The Tenancy Agreement as well as a passport size image of the owner of the land ( in the case of tenants)

Documentation is needed

The National Energy Administration (NEA) operates under the National Development and Reform Commission (NDRC) as the authority to regulate the power industry in China following the first session of the 12th National People’s Congress of China in 2013.

Information that can be useful

Methodology for Shanghai

  • Submit your application for approval to Shanghai Municipal Electric Power Company and then wait for an update on the power supply plan and estimate
  • Agent: Shanghai Municipal Electric Power Company
  • Documents to be submitted with the application: One duplicate of each business license tax registration certificate, organization code registration certificate Certificate of Clearance from the Planning Authority.
  • Time to Completion Time to Complete: 61 calendar days
  • Related Costs: CNY 0
  • Submit the estimate payments in the form of an estimate payment to Shanghai Municipal Electric Power Company and have the designs for the external connection evaluated
    • Agent: Shanghai Municipal Electric Power Company
    • Costs are for cables-laying work, for instance cable-laying on supports that run along the walls, three-phase as well as 5-level Y. Voltage 220/380V 140 kVA, typically require 470+135 bus. YJV200 Model armored construction with flame retardant, approximately 324 Yuan/meter Electricity Meter and installation, mutual inductor: three sets are required 200:5. Three-phase mains: One 250A ABB as well as Schneider Model power distribution box.
    • Time to Completion Time to Complete: 14 calendar days
    • The associated costs: CNY 3,700

Buy the materials and perform the installation

  • Agency Electrical Contractor
  • The items to be bought by the customer are transformer Cabinet for high-voltage switches, Low-voltage Switch Cabinet, wiring cables and other equipment. Materials are readily available locally in Shanghai however, it can take 30-45 days to make the custom-made high – and low-voltage switch cabinets.
  • Time to Completion Time to Completion: 45 calendar days
  • The Associated costs: CNY 187,790
  • Send the report for review to Shanghai Municipal Electric Power Company and wait for the final internal and external inspection
  • AgencyName: Shanghai Municipal Electric Power Company
  • Shanghai Municipal Electric Power Company personnel provide internal wiring inspections and inspections of external installations.
  • Time to Completion Time to Complete: 14 calendar days
  • The associated costs: CNY 0

Install Meter and connection to grid

  • AgencyName: Shanghai Municipal Electric Power Company
  • Shanghai Municipal Electric Power Company offers meter installation and connection to the grid.
  • Time to Completion Time to Completion: 11 calendar days
  • Related Costs: CNY 0

Procedure for Beijing

  • Send your application in writing to State Grid Beijing Electric Power Company and wait for the power supply plan as well as an estimate
  • Agency: State Grid Beijing Electric Power Company
  • Documents to be submitted with the application: One duplicate of each business licence, tax registration certificate , the certificate of registration for organizational codes, Certificate of Clearance from the Planning Authority.
  • Time to Completion Time to Complete: 60 calendar days
  • Related Costs: CNY 0

The State Grid Beijing Electrical Power Company performs external site inspectionsn

  • Agency: State Grid Beijing Electrical Power Company
  • Time to Completion Time to Completion: 11 calendar days
  • The associated costs: CNY 0

Submit payment for estimate to the State Grid Beijing Electric Power Company and have the design of your project for connection to the outside examined

  • Agency: State Grid Beijing Electric Power Company
  • Costs are for cables-laying work, such as cable-laying along supports on the walls, three-phase and 5-level Ys voltage, 220/380V 140 kVA typically requiring 470+135 bus YJV200 Model armored installations with flame retardant, electric installation and meter Mutual inductor: 3 sets are required 200:5. Three-phase mains: One 250A ABB as well as Schneider Model power distribution box.
  • Time to Completion Time to Completion: 14 calendar days
  • Related Costs CNY 3,600

Purchase the material and then conduct the installation

  • Agency: Electrical contractor for the customer.
  • Products to be bought by the customer include transformer Cabinet for high-voltage switches, Low-voltage Switch Cabinet, wiring, cable , and other items.
  • Time to Completion Time to Complete: 50 calendar days
  • The Associated costs: CNY 188,100

Report for submission to State Grid Beijing Electric Power Company and then wait for the final external inspection

  • Agency: State Grid Beijing Electric Power Company
  • State Grid Beijing Electric Power Company personnel inspects outside installations.
  • Time to Completion Time to Complete: 14 calendar days
  • Related Costs: CNY 0

Get installation of the meters and grid connection

  • Agency: State Grid Beijing Electric Power Company
  • State Grid Beijing Electric Power Company offers meter installation and grid connection.
  • Time to Completion Time to Complete: 3 calendar days
  • The associated costs: CNY 0

External Links

State Electricity Regulatory Commission

How To Getting Electricity In China
How To Getting Electricity In China

National Energy Administration (NEA)

China Electricity Council

State Organs

Other

China Electricity Council departments and subordinate units

Reliability Management Center

(State Electricity State Electricity Regulatory Commission Electric Reliability Center)

Establish, manage and supervise the application to ensure the integrity of electric power industry’s management techniques and regulations; statistical assessment of the development of different kinds of electric reliability regulations and codes of statistical analysis responsible for the nation’s electrical reliability statistics data, analysis , and dissemination Electric Reliability Assessment and organizations Security incidents on the grid analysis.

(Tel: 010-63415454, Fax: 010-63415455)